Carrying out a level traverse
To determine the difference in
level between points on the surface of the ground a ‘series’ of levels will need to be carried out; this is called a level traverse or level run.
There are two method of levelling:
Click the link to see the animated rise&fall
methods then click next for the height of collimation method. Please note when the shifting of the staff or level can be done using the rise&fall method
Leveling or Field Procedures
The leveling or field procedure
that should be followed is shown in Figure 1 below.. ![]() Figure 1
Now repeat the steps describe 8 to
10 until you finished at point J.
Field procedures for leveling
All staff readings should be
recorded in the field book. To eliminate errors resulting from any line of sight (or collimation) backsights and foresights should be equal in distance. Length of sight should be kept less than 100 metres. Always commence and finish a level run on a known datum or benchmark and close the level traverse; this enables the level run to be checked.
There are two main methods of
booking levels:
Table
1 Rise & Fall Method
The
millimeter reading may be taken by estimation to an accuracy of 0.005 metres or even less.
While all arithmetic calculations
can be checked there is no assurance that errors in the field procedure will be picked up. The arithmetic check proves only that the rise and fall is correctly recorded in the appropriate rise & fall columns. To check the field procedure for errors the level traverse must be closed. It is prudent to let another student check your reading to avoid a repetition of the level run.
If the arithmetic calculation are
correct, the the difference between the sum of the backsights and the sum of the foresights will equal:
The rise and fall method may take
a bit longer to complete, but a check on entries in all columns is carried out. The RL’s are easier to calculate with the height of collimation method, but errors of intermediate RL’s can go undetected. For this reason students should use the rise and fall method for all leveling exercises.
Always commence and finish a
level run on a datum, benchmark or known RL. This is what is known as a closed level traverse, and will enable you to check the level run. ![]()
Closed
level traverse Series of level runs from a known Datum or RL to a known Datum or RL. Misclosure in millimeter ![]()
Closed loop level traverse
Series of level runs from a known Datum or RL back to the known Datum or RL. Misclosure in millimeter ![]()
Open level traverse
Series of level runs from a known Datum or RL. This must be avoided because there are no checks on misreading |